Construction Company MCA Buyouts

Guide · Business Debt Restructuring

MCA buyouts for construction companies: what a buyer funds against, true buyout vs reverse consolidation, costs, UCC-3 payoffs, and a decision tree.

By The Delancey Street editorial teamUpdated Nov 28, 2026Read 21 minSources 18 cited, checked Nov 2026

An MCA buyout pays off one or more of a construction company’s MCA balances with new money. It lowers cost only if the new terms beat the old ones. A buyout is new financing, so it can cost more than the debt it replaces; compare the total cost and get payoff letters before signing.

Delancey Street negotiates with funders and creditors; independent counsel handles legal matters. Delancey Street is not a law firm. No outcome is promised; results vary.

🛡
Delancey Street is a business debt settlement firm, not a law firm. We negotiate with funders on your behalf and bring in independent attorneys only when a situation requires it.

Key takeaways

  • Only a bankruptcy plan can bind a creditor that refuses: Chapter 11 or Subchapter V for companies, Chapter 13 for eligible individual owners (11 U.S.C. §1327(a)).
  • Construction managers held 609,100 jobs in 2025, employment is projected to grow 9% from 2025 to 2035, and 38% are self-employed (BLS Occupational Outlook Handbook).
  • Debts secured by excavators, loaders, trucks and trailers, and trust-fund taxes (the trust-fund portion of Form 941 payroll taxes), are not discounted like unsecured debt.
  • Get payoff letters and confirm each UCC-3 termination after payoff; sold-receivables filings follow their own rule (UCC §9-513(c)(2)). A “buyout” that only funds the business is a reverse consolidation.
  • General information, not legal or tax advice; results vary.

Fast facts: MCA buyouts for construction companies (2026)

$2,186.1BU.S. construction spending, September 2026 (seasonally adjusted annual rate)

2.7% (±1.5%) below September 2025, so less new work is chasing the same crews.

Source: U.S. Census Bureau, Construction Spending (CB26-176, Nov 2, 2026) · Checked Nov 2026

+27.6%Steel mill product prices, Sept 2025 to Sept 2026

Section 232 tariffs of 50% have applied to most imported steel and aluminum since June 2025.

Source: AGC Construction Inflation Alert, Oct 2026 (BLS PPI data) · Checked Nov 2026

91%Site example: a renewal giving $28,200 of new cash costs $25,800

Why a buyout must beat the old total cost, not just the old debit.

Source: Delancey Street worked example (site standard) · Checked Nov 2026

20 daysUCC-3 termination after demand, when no obligation or commitment remains

Sold-accounts filings, the typical MCA filing, follow §9-513(c)(2) instead.

Source: UCC §9-513, Cornell LII · Checked Nov 2026

Site guidance. Settlement-based programs: site planning range 3–18 months — not a firm timeline or promise. MCA debits above 20% of average daily deposits fall in this site’s danger band (see the calculator below; site guideline).

How does an MCA buyout work for a construction company?

A new funder or lender pays off one or more existing MCA balances directly, using payoff letters, and the business then repays the new funder on new terms. The old debits stop only when each payoff closes. A buyout lowers cost only when the new total cost is below what you still owe on the old advances.

Think of a buyout as a replacement offer. Compare three things before signing: the new debit against the old ones, the new total cost against the old remaining balance, and what the new agreement reaches. A lower daily debit can still cost more in total if the new factor applies to the whole balance.

A true buyout sends the money to the old funders, not to you. If an offer sends cash to the business and leaves the old advances in place, it is a reverse consolidation. The pillar guide Merchant Cash Advance Buyouts covers buyouts for every industry.

Terms on this page

MCA buyout
New money that pays off one or more MCA balances.
True buyout
A buyout where the new funder pays the old balances directly, shown by payoff letters.
Reverse consolidation
A new MCA that funds the business to keep paying old advances; it adds a position.
MCA payoff letter
A funder’s written statement of the amount that ends the contract.
UCC-3 termination
A filing that ends a UCC financing statement after payoff.
MCA factor rate
The multiple that sets total repayment, such as 1.35 times the advance.

Why do construction companies end up looking at MCA buyouts?

Because one or more fixed debits no longer fit the pay-app cycle, and a buyout promises one new payment. What a buyer funds against matters: your deposit history, receivables from project owners and GCs, and existing liens on equipment. Read the new agreement’s receipts and collateral terms before signing, and compare total cost.

Deposit history. A buyout funder will want bank statements; underwriting rules differ by funder. A construction company’s deposits swing with job timing: cash arrives after pay applications are approved, with retainage held back. The firm’s article on fronting costs while waiting on retainage gives 5% and 10% examples. Those swings show in the history the funder reviews.

Receivables from owners and GCs. The new agreement’s receipts and collateral definitions decide what it reaches — possibly receivables and retainage owed by project owners and general contractors. Read both definitions before signing.

Equipment and existing liens. Excavators, loaders, trucks or trailers may already carry liens. A buyout adds a new UCC-1 filing, and each old position needs a payoff letter and a UCC-3 after payment.

The cost backdrop. AGC reports steel mill product prices up 27.6% in the year to September 2026, so margins are tight. A new factor cost on the whole balance must beat the old total cost. The company-wide view is on Business Debt Restructuring for Construction Companies.

How do buyout options compare for a company?

A true buyout pays balances directly; a partial buyout pays only some positions; a loan refinance replaces advances with a bank or SBA loan; a reverse consolidation funds the business and leaves the balances. Settlement and reconciliation add no new money. Each lowers the payment only under conditions, and several can raise total cost.

General information, not legal advice. Typical, not a guarantee.

MCA buyout options for construction companies
OptionWho fundsLowers the payment?Raises total cost?Construction company catch
True buyoutA new funder pays the balances directlySometimes — if the new debit is lowerDepends — a new factor cost on the wholeWatch Payoff letters and UCC-3s needed; the new funder’s UCC-1 and receipts definition may reach receivables from project owners and GCs.
Partial buyoutA new funderSometimes — only for the positions paid off, and only if the new debit is below the ones it replacesDepends — a new factor cost on the bought-out amountWatch Remaining positions keep debiting.
Refinance into a loanA bank or SBA lenderSometimes — if a lender approves and the new payment is below the old debitsSometimes — a longer term can add interestWatch SBA restricts 7(a) refinancing of sales-based advances (MCAs); eligibility is conditional — a lender confirms. Equity in excavators, loaders, trucks or trailers may be pledged.
Reverse consolidationA new funder funds the business, not the balancesSometimes, temporarilyHigher risk Yes in total — adds a positionNot a buyout of the balance.
Settlement (comparison)No new money — each funderSometimes — only after each funder signs; lump sums may be requiredNo new financing cost; fees and tax applyWatch Old debits continue until each funder signs.
Reconciliation (comparison)None — a contract rightSometimes — if sales fellNoOnly if the contract has the clause.

How much of your company’s deposits goes to MCA payments?

In this page’s example, a construction company with $250,000 of monthly deposits and two MCAs — $1,200 daily and $5,000 weekly — pays about $47,674 a month in MCA debits, or 19.1% of deposits. That is in the Strained band, just under this site’s 20% danger line. One slow pay app can push it over.

This calculator measures MCA debits against deposits only. It leaves out loans, leases, payroll, materials and taxes, so it cannot say whether the business is sustainable. Count deposits actually received, not pay apps billed or retainage still held. A prime contractor’s deposits include money owed to subs and suppliers, so the percentage understates the squeeze; see Business Debt Restructuring for General Contractors.

To test a buyout offer, run the calculator twice: once with your current debits, once with the new debit in place of the positions it pays off.

MCA burden calculator

Example numbers — replace with yours.

MCA burden19.1%19.1%
BandStrained
Monthly MCA debits$47,674
Left after MCA debits$202,326

Your 2 MCA payments take about 19.1% of your deposits — about $47,674 a month, leaving $202,326. That is in the strained range on this site’s guideline.

Bands are the site’s guideline, not a law or industry standard: under 10.0% Manageable; 10.0–20.0% Strained; over 20.0% Danger zone. Estimate only. Your inputs stay in your browser.

Static check for the example inputs ($250,000 deposits; $1,200 daily + $5,000 weekly)

MCA burden for the example inputs
StepResult
Total daily MCA debits (weekly ÷ 5)$2,200
Average daily deposits (deposits ÷ 21.67)$11,536.69
MCA burden19.1% — Strained
Monthly MCA debits (daily total × 21.67, rounded half up)$47,674
Left after MCA debits$202,326
Sample results: same two MCAs, different monthly deposits
Monthly depositsMCA burdenMonthly MCA debitsLeft after MCA debitsBand
$150,00031.8%$47,674$102,326Danger zone
$200,00023.8%$47,674$152,326Danger zone
$250,00019.1%$47,674$202,326Strained
$300,00015.9%$47,674$252,326Strained
$400,00011.9%$47,674$352,326Strained

Site check: $120,000 of deposits with $650 + $750 daily gives 25.3%, $30,338 a month and $89,662 left — Danger zone. One slow pay app can push the example over 20%.

How this is calculated. Weekly debits are converted to daily at weekly ÷ 5. Average daily deposits = monthly deposits ÷ 21.67 business days. Burden = total daily debits ÷ average daily deposits × 100, shown to one decimal (half up). Monthly debits = total daily × 21.67, rounded to whole dollars (half up); “left after” = deposits − rounded monthly debits. Bands use the displayed percentage.

Job cash gap. Deposits are only half the story for a construction company. The job cash gap calculator shows the cash one job ties up before the client pays. On the example job — a $600,000 contract over 6 months, Net 60, 10% retainage and 85% job cost — spending runs $85,000 a month and the deepest gap is $170,000 in month 2.

Job cash gap calculator

Example numbers — replace with yours.

Spend a month$85,000
Deepest gap$170,000
WhenMonth 2
Share of contract28.3%
Your deepest cash gap is about $170,000 in month 2 — money you must carry before the client pays.
Gap by month (spent minus collected)
MonthGap
Month 1$85,000
Month 2$170,000
Month 3$165,000
Month 4$160,000
Month 5$155,000
Month 6$150,000
Month 7$60,000
Month 8−$30,000
Month 9−$90,000

Leaves out change orders, mobilization or front-loaded billing, overhead, existing debt payments and taxes. Shows one job; overlapping jobs add their gaps month by month. Estimate only; your numbers stay in your browser.
Sample results
Inputs (contract · months · terms · retainage · job cost)Largest gapMonth
Default: $600,000 · 6 mo · Net 60 · 10% · 85% (retainage of $60,000 collected in month 9)$170,0002
Test 2: $300,000 · 4 mo · Net 90 · 5% · 80%$180,0003
Test 3: $1,200,000 · 8 mo · Net 60 · 10% · 88%$264,0002
How this is calculated

Billing each month = contract ÷ months. Spend each month = contract × job cost % ÷ months. Each bill is collected after the payment-terms lag (Net 30 = 1 month, Net 60 = 2, Net 90 = 3), minus retainage. All retainage is collected in month (months + lag + 1). Gap = cumulative spend − cumulative collections. The calculator reports the largest gap and its month.

Run the job gap for each open job and add the gaps. A new buyout debit has to fit inside that total, not just inside average deposits.

What does each path cost?

A buyout costs a new factor or interest charge, any origination or admin fees, UCC filings, and sometimes a broker fee. Compare that with what you still owe on the old advances. A renewal instead of a buyout can cost almost as much as the cash it provides. Get every cost in writing; there is no single total.

Convert any factor rate to a comparable cost with the MCA Effective APR Calculator before you compare offers.

What each path really costs a construction company
Cost itemWho charges itTypical rangeNote
New factor or interest costFunder or lenderPer the disclosure; convert a factor cost with the APR calculatorRun the replacement-offer comparison.
Origination or admin feesFunder or lenderPer the disclosureAsk for them in writing.
UCC-3 terminations (old) and a new UCC-1Funders; state filing officeState fee, per state§9-513(c)(1) for ordinary loans; sold-receivables filings follow (c)(2).
Broker feeBrokerDisclosed in writingAsk who pays it and how much.
Cost scale of a renewal insteadThe funderSite renewal example: $28,200 of new cash for a $25,800 cost (91%)Shows why a buyout must beat the old total cost.

Typical ranges, not quotes; results vary.

What happens to your excavators, loaders, trucks and trailers, receivables and personal guarantee?

Each asset follows its own documents. A lender with a lien on equipment keeps it until paid, and a funder that bought receivables can notify project owners and GCs to pay it. After a buyout, the old funders’ filings end only after payoff, and the new funder may file its own. Your guarantee survives unless a release names you.

Excavators, loaders, cranes, trucks and trailers

Check which case is yours for each item. Owned with a lien: the lender holds a security interest. Owned free and clear: no lender claim. Leased: the lessor owns it; a true lease is not a security interest (UCC §1-203), so the lease terms control. The loan or security agreement, the lease, the title and a state UCC search show your case.

Receivables and retainage

Project owners and general contractors that approve pay applications owe the business, and the retainage they hold is a receivable too. A funder that bought or holds an interest in receivables may notify them to pay it instead (UCC §9-406(a)); they may ask for reasonable proof (§9-406(c)). Counsel reads any notice.

Yard or shop, if owned

Real property sits outside UCC Article 9 (§9-109(d)(11)), so a mortgage on an owned yard or shop follows state real-estate law. An attorney reads the mortgage and any guaranty that comes with it.

The bonding line, if bonded

Bonding capacity is not collateral. The surety’s general indemnity agreement and bond terms may require notice or consent before new debt or liens; an attorney reads the actual agreement. No payment path here is shown as improving bonding.

A secured lender may repossess collateral without a breach of the peace (UCC §9-609), then sell it in a commercially reasonable way and claim any shortfall (§9-610, §9-615). A deficiency may settle for about 30–60% of the deficiency — a typical reported range, not a guarantee. In the site’s deficiency example, $80K owed plus $4.5K of costs minus a $41K sale leaves $43.5K. Settling unsecured debt does not remove a lien.

A personal guarantee is released only by a writing that names the guarantor, and the automatic stay never protects a guarantor (11 U.S.C. §362(a)). At payoff of an ordinary secured loan with no commitment to advance, the lender must terminate its UCC filing within 20 days of an authenticated demand (UCC §9-513(c)(1)); filings on sold receivables, the typical MCA filing, follow §9-513(c)(2), and counsel confirms which applies. More: UCC 9-406 explained, whether MCA funders can contact your customers and equipment, receivables, bonds and liens on the construction hub.

The project side. The business’s own mechanics’ lien or bond-claim rights against an owner or GC are an asset, with deadlines that can lapse while you shop offers; deadlines vary by state, so counsel calendars them. After a buyout pays a funder that sent §9-406 notices, get written withdrawal of those notices.

When do MCA buyouts fit a construction company — and when don’t they?

A buyout fits when the new total cost is lower, payoff letters confirm the balances are paid directly, there is no lawsuit or COJ, deposits carry the new payment, and only one or two positions are involved. It doesn’t fit when the offer is a reverse consolidation, total cost rises, you are sued or the business isn’t viable.

A buyout fits when

  • The new total cost is lower (replacement-offer comparison).
  • Payoff letters confirm the balances are paid directly.
  • No lawsuit or confession of judgment has landed.
  • Deposits carry the new payment alongside crew payroll, materials, equipment notes and leases, insurance and bonding premiums.
  • One or two positions are involved, not a stack.

It doesn’t when

  • The offer funds the business but leaves the balances (a reverse consolidation).
  • Total cost rises.
  • You are sued or a COJ was filed → attorney first (decision tree card 1).
  • The business is not viable → wind-down options with an attorney and a CPA.
  • The only buyer is another short-term funder at a higher factor.

Operating costs that must stay covered in any path: crew payroll, materials, equipment notes and leases, insurance and bonding premiums.

Bottom line: compare total cost and confirm every payoff in writing. Where one small creditor is the whole problem, an owner can call that creditor directly.

Which path fits your company?

Answer up to six questions. A lawsuit, frozen account, repossession, levy, or a lien or bond claim on one of your jobs goes to an attorney first. Then the tree asks about MCAs, viability, whether the offer pays balances directly, whether the new total cost is lower, and whether deposits carry the new debit.

The tree never uses the calculator percentage as an affordability verdict. A construction company with no MCAs is pointed to consolidation and never sees MCA services.

Is a buyout right for your company? A decision tree

Answer up to 6 short questions. The lawsuit question comes first.

Every route, in plain text

  1. If a creditor has sued, filed a confession of judgment, frozen an account, or sent a repossession or levy notice, or a mechanics’ lien or bond claim has been filed on one of your jobs (or you are not sure) → talk to an independent attorney now; stop here. See Business Debt Lawsuits and What Happens When a Business Bank Account Is Frozen?.
  2. If the business has no MCA → no MCA: see consolidation instead: Business Debt Consolidation for Construction Companies.
  3. If the offer does not pay the old balances directly → it is a reverse consolidation; compare it with settlement: True Buyout vs Reverse Consolidation.
  4. If the offer pays the balances directly, the new total cost is lower and deposits carry the new debit → a buyout may fit: Merchant Cash Advance Buyouts and MCA Buyout Alternatives.
  5. If the new total cost is not lower, or deposits cannot carry the new debit → settlement or reconciliation: MCA Buyout vs Debt Settlement and how a reconciliation request works. Two or more MCAs: also How to Restructure Multiple MCAs for Construction Companies.
  6. If the construction company could not keep running even with reduced payments → wind-down options with an attorney and a CPA: an assignment for the benefit of creditors, a negotiated sale or Chapter 7, where a company gets no discharge (11 U.S.C. §727(a)(1)). Guarantees survive. See Alternatives to Chapter 7 Business Bankruptcy.
  7. If viability, payoff letters, the cost comparison or the new debit is unclear → build a debt schedule (How to Create a Business Debt Schedule) and a 13-week cash forecast (How to Build a 13-Week Cash Flow Forecast), then review with a CPA or attorney; see The Delancey Debt Review. Not sure about payoff letters: ask the funder for them before signing. “Not sure” never routes to wind-down.

General information, not legal or financial advice.

Other routes for your construction company. Replacing an MCA with cheaper financing: MCA Refinancing for Construction Companies. Handling several positions one by one: How to Restructure Multiple MCAs for Construction Companies.

MCA buyouts FAQs for construction companies

Can a construction company get an MCA buyout while staying open?

Possibly, if a funder or lender approves. A buyout is new financing: the new money pays the old balances, and a new debit or loan payment starts. Old debits continue until each payoff closes. Compare total cost first, because a buyout can cost more than the debt it replaces.

What is the difference between a buyout and a reverse consolidation?

A true buyout pays the old balances directly, and payoff letters prove it. A reverse consolidation sends money to the business and leaves the old advances in place, so you keep paying them while adding a new position. See True Buyout vs Reverse Consolidation before signing anything called a buyout.

Will a buyout remove the UCC lien?

Only after payoff, and only the old funders’ filings. Ordinary secured loans must be terminated within 20 days of an authenticated demand (UCC §9-513(c)(1)); filings on sold receivables follow §9-513(c)(2). The new funder may file its own UCC-1, so a lien can remain under new ownership.

Is a buyout cheaper than settlement?

It depends. A buyout adds a new factor or interest cost but avoids settlement fees and possible tax on forgiven debt. A settlement can lower the balance but needs each funder’s agreement and can affect credit. Compare total cost, tax and credit side by side; MCA Buyout vs Debt Settlement walks through both.

Will negotiating stop a lawsuit or frozen account?

No. Negotiating does not pause a lawsuit, a court deadline or a frozen account, and deadlines keep running while you talk. Call an independent attorney right away. The automatic stay exists only in bankruptcy, and it protects the debtor, never an owner-guarantor (11 U.S.C. §362(a)). Delancey Street is not a law firm.

Am I personally liable if the construction company closes — and does it matter if I’m a sole proprietor?

Possibly. Personal guarantees survive closure, an assignment for the benefit of creditors and a company’s Chapter 7, and a release must name you. A responsible person who willfully fails to pay withheld payroll taxes faces the TFRP (§6672). A sole proprietor owes business debts personally: Chapter 7, Chapter 13 (one $2.75M limit from Nov 10, 2026) or Subchapter V. Ask an attorney.

Is forgiven business debt taxable?

Generally yes, unless a §108 exclusion applies, such as a bankruptcy case or insolvency. Example: an S corporation, tested at the corporation, with $120K assets, $200K liabilities and $90K forgiven has $10K taxable. No income arises where paying would have been deductible. A 1099-C comes at $600+ from applicable entities only; debt can be taxable with no form. Ask a CPA.

Will my surety see it if I take an MCA buyout?

Possibly. A new funder’s UCC-1 is a public filing, and sureties review a contractor’s finances when setting bonding capacity; ask your surety agent what it reviews. This page makes no claim that a buyout helps or hurts bonding. Talk to the surety agent before you sign, not after.

What to do this week

  1. Build a debt schedule listing every debt, creditor, balance and payment — see How to Create a Business Debt Schedule.
  2. Run the MCA burden check with your current debits and again with any offer’s new debit.
  3. Update the WIP schedule and the bond list, and list every excavator, loader, truck or trailer loan or lease (lender, balance, lien status); tell your surety agent before talks start — see equipment, receivables, bonds and liens on the construction hub.

Get a free review of your options

  1. List each debt with its creditor, balance and payment.
  2. We review your contracts, balances and cash flow with you.
  3. You get a plain-English summary of your options, with no obligation.
Start my free review

Sources

  1. Construction Spending (release CB26-176, Nov 2, 2026) — U.S. Census Bureau — census.gov — Checked Nov 2026
  2. Construction Inflation Alert, October 2026 — Associated General Contractors of America — agc.org — Checked Nov 2026
  3. Occupational Outlook Handbook: Construction Managers — U.S. Bureau of Labor Statistics — bls.gov — Checked Nov 2026
  4. About Form 1099-C, Cancellation of Debt — IRS — irs.gov — Checked Nov 2026
  5. UCC §9-109, Scope of Article 9 — Cornell LII — law.cornell.edu — Checked Nov 2026
  6. UCC §9-406, Discharge of account debtor; notification of assignment — Cornell LII — law.cornell.edu — Checked Nov 2026
  7. UCC §9-513, Termination statement — Cornell LII — law.cornell.edu — Checked Nov 2026
  8. UCC §9-609, Secured party’s right to take possession after default — Cornell LII — law.cornell.edu — Checked Nov 2026
  9. UCC §9-610, Disposition of collateral after default — Cornell LII — law.cornell.edu — Checked Nov 2026
  10. UCC §9-615, Application of proceeds of disposition; liability for deficiency — Cornell LII — law.cornell.edu — Checked Nov 2026
  11. UCC §1-203, Lease distinguished from security interest — Cornell LII — law.cornell.edu — Checked Nov 2026
  12. 11 U.S.C. §362, Automatic stay — Cornell LII — law.cornell.edu — Checked Nov 2026
  13. 11 U.S.C. §1327, Effect of confirmation (Chapter 13) — Cornell LII — law.cornell.edu — Checked Nov 2026
  14. 11 U.S.C. §727, Discharge (Chapter 7) — Cornell LII — law.cornell.edu — Checked Nov 2026
  15. H.R. 7730 (bankruptcy debt limits) — Congress.gov — congress.gov — Checked Nov 2026
  16. 26 U.S.C. §108, Income from discharge of indebtedness — Cornell LII — law.cornell.edu — Checked Nov 2026
  17. 26 U.S.C. §6672, Failure to collect and pay over tax — Cornell LII — law.cornell.edu — Checked Nov 2026
  18. Topic no. 431, Canceled debt — is it taxable or not? — IRS — irs.gov — Checked Nov 2026
Business debt questions? A senior advisor replies fast. Free, confidential.Free review